📘 Program Maisha Baada ya Chuo Kama Civil Engineer/Technician
Program Hii Ni Maalum Kwa Wahitimu Watarajiwa Civil Engineers/Technicians TU!
Kupitia Program Hii Utaenda Kupata Majibu ya Maswali yote yanayokutatiza na Kukunyima RAHA kama Mhitimu Mtarajiwa Kada ya Civil Engineering Ngazi ya (Diploma au Bachelor) Kila Unapowaza Maisha Baada ya Kumaliza Chuo Kama:
- Nitaanzia wapi baada ya kumaliza chuo, kabla sijaajiriwa na sina mtaji?
- Nitaanzia wapi kutengeneza pesa baada ya kumaliza chuo?
- Jinsi ya kutumia elimu yako ya kitaalamu ya "Civil Engineering" kujikwamua kiuchumi.
- Msingi wa kujiajiri moja kwa moja ikiwa ajira za makampuni binafsi na serikali zitakuwa changamoto.
- Nitapata vipi "connections" zitakazonisaidia kupata kazi?
- Jinsi ya kujenga uzoefu utakao kusaidia kupata kazi katika makampuni makubwa.
- Vitu gani vitakavyomfanya mhitimu wa Civil Engineering aweze kuendesha mradi mpaka mwisho kwa ufanisi?
- Itachukua muda gani kujiajiri au kupata ajira kama Civil Engineer/Technician?
- Je, nianze kufanya kazi inayohusiana na taaluma yangu ya Civil Engineering au kazi yeyote itakayopatikana kwa wakati huo?
- Nitaanzaje au nitaanzia wapi kuishi na kufanya kazi katika taaluma yangu ya Civil Engineering?
- Baada ya kumaliza chuo, nitawezaje kupata fursa za kuendeleza taaluma yangu kabla sijapata ajira?
- Tofauti zilizopo kati ya kufanya kazi kwa mkandarasi, Kujiajiri na kuajiriwa serikalini kama “Civil Engineer/Technician”.
- Ni changamoto gani zipo kwenye soko la ajira kwa sasa?
At a construction site, civil engineers and technicians manage, supervise and performs different tasks, some of which are very typical and repetitious in nature such as concrete work, schedule of material preparation, steel fixing etc.
So, here are quick guide to some points, suggestions, and tips that a site civil engineer and technician should keep in mind for quick calculations and rapid answers to site challenges and problems.
Before we continue please click ==> HERE to support my YouTube channel this motivate me to keep producing good content like this.
Read also;
Let continues...
The following are some basic useful tips during site work for civil engineers and technicians to keep in mind when working on a construction site.
1. Cover of concrete to the reinforcement shall be, unless shown otherwise;
Minimum: 20 mm (Varies from that depending upon Exposure condition and Fire Resistance) [Ref BS 8110:1997]
- Base - 50mm minimum to main bars
- Beams - 25mm minimum to main bars
- Slab - 15mm minimum to main bars
- Wall - 25mm minimum to main bars
- Raft slab - 100mm minimum to main bars
- Columns - 40mm minimum to main bars
- Weight of cement one bag 50 Kg
- Volume of cement bag 35 Litres (0.035m3 )
- Density of loose cement 1440 Kg /m3
- Specify gravity of cement 3.15
- One meter cubic of cement equal to 29 cement Bags
- Cement strength class for OPC is 32.5N, 42.5N and 52.5N
- M 10 – 1 : 4 : 8 Used as a Blinding Concrete
- M 15 – 1 : 3 : 6 Used as a Plain Concrete
- M 20 – 1 : 2 : 4 Used as a Reinforced Concrete
- M 25 – 1 : 1.5 : 3 Used as a Reinforced Concrete
- M 30 – 1 : 1 : 2 Used as a Reinforced Concrete
- M 35 and Above - Special Concrete (Design Mix)
- 8mm - 4.736 Kg
- 10mm - 7.4 Kg
- 12mm - 10.67 Kg
- 16mm - 18.96 Kg
- 20mm - 29.63 Kg
- 25mm - 46.30 Kg
- 32mm - 75.85 Kg
- 40mm - 118.52 Kg
- 8mm - 211
- 10mm - 135
- 12mm - 94
- 16mm - 53
- 20mm - 34
- 25mm - 22
- 32mm - 13
- 40mm - 8
- Initial setting time should not be less than 30 minutes.
- Final setting time should not be greater than 10 hours.
- Inner plaster work : 10-12mm
- Outer plaster work: 15-20mm
- Ceiling plaster work: 6-8mm
- Cement - 2%
- Concrete - 2 to 3%
- Sand - 7 to 10%
- Tiles - 10%
- Aggregate - 3 to 5%
- Bricks - 5%
- Steel - 3 to 5%
- Concrete (PCC) - 2400 Kg /m3
- Steel - 7850 Kg /m3
- Concrete (RCC) - 2500 Kg /m3
- Water - 1000 Kg /m3
- Glass - 2530 Kg /m3
- Cement - 1440 Kg /m3
- Sand - 1600 to 1840 Kg /m3
- Asphalt concrete surfaces 2.5%
- Surface dressing surfaces 3.0%
- Stone paved surfaces 3.0%
- Gravel and earth surfaces 4.0%
- 1 – 5 m3 : 1 No.
- 6 – 15 m3 : 2 No..
- 16 – 30 m3 :3 No.
- 31 -50 m3 : 4 No.
- Above 50 m3 : 4 + 1 no. of addition for each 50 m3.