At a construction site, civil engineers and technicians manage, supervise and performs different tasks, some of which are very typical and repetitious in nature such as concrete work, schedule of material preparation, steel fixing etc.
So, here are quick guide to some points, suggestions, and tips that a site civil engineer and technician should keep in mind for quick calculations and rapid answers to site challenges and problems.
Before we continue please click ==> HERE to support my YouTube channel this motivate me to keep producing good content like this.
Read also;
Let continues...
The following are some basic useful tips during site work for civil engineers and technicians to keep in mind when working on a construction site.
1. Cover of concrete to the reinforcement shall be, unless shown otherwise;
Minimum: 20 mm (Varies from that depending upon Exposure condition and Fire Resistance) [Ref BS 8110:1997]
- Base - 50mm minimum to main bars
- Beams - 25mm minimum to main bars
- Slab - 15mm minimum to main bars
- Wall - 25mm minimum to main bars
- Raft slab - 100mm minimum to main bars
- Columns - 40mm minimum to main bars
- Weight of cement one bag 50 Kg
- Volume of cement bag 35 Litres (0.035m3 )
- Density of loose cement 1440 Kg /m3
- Specify gravity of cement 3.15
- One meter cubic of cement equal to 29 cement Bags
- Cement strength class for OPC is 32.5N, 42.5N and 52.5N
- M 10 – 1 : 4 : 8 Used as a Blinding Concrete
- M 15 – 1 : 3 : 6 Used as a Plain Concrete
- M 20 – 1 : 2 : 4 Used as a Reinforced Concrete
- M 25 – 1 : 1.5 : 3 Used as a Reinforced Concrete
- M 30 – 1 : 1 : 2 Used as a Reinforced Concrete
- M 35 and Above - Special Concrete (Design Mix)
- 8mm - 4.736 Kg
- 10mm - 7.4 Kg
- 12mm - 10.67 Kg
- 16mm - 18.96 Kg
- 20mm - 29.63 Kg
- 25mm - 46.30 Kg
- 32mm - 75.85 Kg
- 40mm - 118.52 Kg
- 8mm - 211
- 10mm - 135
- 12mm - 94
- 16mm - 53
- 20mm - 34
- 25mm - 22
- 32mm - 13
- 40mm - 8
- Initial setting time should not be less than 30 minutes.
- Final setting time should not be greater than 10 hours.
- Inner plaster work : 10-12mm
- Outer plaster work: 15-20mm
- Ceiling plaster work: 6-8mm
- Cement - 2%
- Concrete - 2 to 3%
- Sand - 7 to 10%
- Tiles - 10%
- Aggregate - 3 to 5%
- Bricks - 5%
- Steel - 3 to 5%
- Concrete (PCC) - 2400 Kg /m3
- Steel - 7850 Kg /m3
- Concrete (RCC) - 2500 Kg /m3
- Water - 1000 Kg /m3
- Glass - 2530 Kg /m3
- Cement - 1440 Kg /m3
- Sand - 1600 to 1840 Kg /m3
- Asphalt concrete surfaces 2.5%
- Surface dressing surfaces 3.0%
- Stone paved surfaces 3.0%
- Gravel and earth surfaces 4.0%
- 1 – 5 m3 : 1 No.
- 6 – 15 m3 : 2 No..
- 16 – 30 m3 :3 No.
- 31 -50 m3 : 4 No.
- Above 50 m3 : 4 + 1 no. of addition for each 50 m3.